Fixes #29032.
2003-08-27 Hans Petter Jansson <hpj@ximian.com> Fixes #29032. * gui/dialogs/task-details-page.c (status_changed): When task status is set to "In Progress", set percent complete to 50% only if it was previously set to 0% or 100%. svn path=/trunk/; revision=22395
This commit is contained in:

committed by
Hans Petter

parent
15c8a15ba1
commit
405d1070bf
@ -1,3 +1,11 @@
|
||||
2003-08-27 Hans Petter Jansson <hpj@ximian.com>
|
||||
|
||||
Fixes #29032.
|
||||
|
||||
* gui/dialogs/task-details-page.c (status_changed): When task status
|
||||
is set to "In Progress", set percent complete to 50% only if it was
|
||||
previously set to 0% or 100%.
|
||||
|
||||
2003-08-27 Bolian Yin <bolian.yin@sun.com>
|
||||
|
||||
* gui/Makefile.am use libevolution-calendar-a11y instead of libevolution-a11y.
|
||||
|
@ -594,7 +594,10 @@ status_changed (GtkMenu *menu, TaskDetailsPage *tdpage)
|
||||
e_date_edit_set_time (E_DATE_EDIT (priv->completed_date), ctime);
|
||||
complete_date_changed (tdpage, 0, FALSE);
|
||||
} else if (status == ICAL_STATUS_INPROCESS) {
|
||||
gint percent_complete = e_dialog_spin_get_int (priv->percent_complete);
|
||||
if (percent_complete <= 0 || percent_complete >= 100)
|
||||
e_dialog_spin_set (priv->percent_complete, 50);
|
||||
|
||||
e_date_edit_set_time (E_DATE_EDIT (priv->completed_date), ctime);
|
||||
complete_date_changed (tdpage, 0, FALSE);
|
||||
} else if (status == ICAL_STATUS_COMPLETED) {
|
||||
|